Construction Update
Current Parking Structure Committee Minutes
Cardinal House Comes Down!
Plat of Topography
- Plat of Topography, 10 Aug 2011
Tentative Construction Schedule
- November 2011 - February 2012:
- Current south parking area will be available through Ash Wednesday
- No construction work planned
- March - July 2012:
- Install shoring on Cardinal House property
- Demolition and grading of south parking site, Prayer Garden wall removed, Install foundations and retaining walls, Begin setting precast structure
- August - October 2012:
- Finish setting precast structure, Install surfaces on deck and slag on-grade, Re-build/replace prayer garden wall, Landscape
Parking Structure Committee and Partners
Committee Members: Tom Schmitz (chair), Fr. Jon Seda, Bob Lehmann, Carl Bern, Doug Hartwell, Harlan Hanson, John Klaus, Kerry Dixon-Fox, and Bobby LeBlanc.
Partners: RDG Planning/Design; HPC, LLC (Harold Pike Construction Company)