Tentative Construction Schedule

November 2011 - February 2012:
Current south parking area will be available through Ash Wednesday
No construction work planned
March - July 2012:
Install shoring on Cardinal House property
Demolition and grading of south parking site, Prayer Garden wall removed, Install foundations and retaining walls, Begin setting precast structure
August - October 2012:
Finish setting precast structure, Install surfaces on deck and slag on-grade, Re-build/replace prayer garden wall, Landscape

Parking Structure Committee and Partners

Committee Members: Tom Schmitz (chair), Fr. Jon Seda, Bob Lehmann, Carl Bern, Doug Hartwell, Harlan Hanson, John Klaus, Kerry Dixon-Fox, and Bobby LeBlanc.

Partners: RDG Planning/Design; HPC, LLC (Harold Pike Construction Company)
RDG Planning/Design; Harold Pike Construction Company