Construction Update
Current Parking Structure Committee Minutes
Construction Photos
- Slideshow of Construction Photos
Cardinal House Comes Down!- (14 images): [ medium | large ]
Construction Milestones
timeline, updated 27 June 2012
- Excavation and Grading
- March - April
- Install footings/walls
- April - June
- Set Pre-cast & pour decks/slab-on-grade etc
- July - September
- New South Entrance
- September - October
- Landscaping
- October
- Finish work - signage, lighting, etc
- November
Parking Structure Committee and Partners
Committee Members: Tom Schmitz (chair), Fr. Jon Seda, Bob Lehmann, Carl Bern, Harlan Hanson, John Klaus, Kerry Dixon-Fox, and Bobby LeBlanc.
Partners: RDG Planning/Design; HPC, LLC (Harold Pike Construction Company)